Kitchen handover: 24 items to check at acceptance
Taking handover of a new kitchen — the 24-item acceptance checklist covering temperature, flame, water, electrical, gas and documentation.
Handover is the critical moment
The most critical moment of a new kitchen installation is handover. The acceptance protocol signed here lays the foundation for warranty, liability and service for the next 5-10 years.
What we see in the field: most operators say "looks like everything works" and sign. Three months later — a fryer thermostat fault, hood plenum leak, gas-line pressure loss — and because it was "accepted", the dispute begins.
Here's the 24-item acceptance checklist we use in the field. Each item should be marked done / not done / note and attached to the protocol.
A. Visual and general (4 items)
1. Visible damage check
No scratch, dent or deformation on stainless surfaces. Glass surfaces (pizza oven door) crack-free, door gaskets intact.
2. Label and serial number
Each unit's nameplate legible, CE label present, serial matches handover doc.
3. Accessory completeness
Baskets (fryer), trays (oven), GN pans (bain-marie), spare keys, manuals — match packing list.
4. Alignment and level
All equipment plumb on a spirit level. Line equipment flush, no more than 2 mm height delta between units.
B. Electrical (5 items)
5. Ground continuity
Each unit's ground line tested with a meter. < 0.1 Ω continuous resistance required. Otherwise shock risk.
6. Phase balance
On 3-phase equipment, panel-side current per phase should be close. Imbalance → balance the load — long-term, burns motors.
7. Breaker groups
Verify each unit on its own breaker group at the panel. Labels legible.
8. Grounded socket test
For standalone plug-in equipment, grounded socket test (live/neutral/ground correct).
9. Emergency stop test
The emergency stop button on the main panel — pressing should cut all cooking equipment (ventilation and lighting may stay).
C. Gas (4 items)
10. Leak test
The full gas line checked with soap-bubble test. No bubbles at any joint. Performed by professional, documented in writing.
11. Pressure test
Verify regulator outlet pressure (natural gas 20 mbar, LPG 30 mbar) with a manometer.
12. Fire damper
Hood-interlock gas shutoff tested — fire detection or manual trigger cuts gas.
13. Gas detector
If installed, calibrated test gas triggers the alarm. Response under 30 seconds.
D. Water and drainage (3 items)
14. Water in and out
Ice machine, dishwasher, steamer — no leaks, correct supply pressure (typically 2-4 bar).
15. Drain flow
Kitchen floor drain, dishwash drain, hood drain — test by pouring water; check flow rate and back-up.
16. Hot water temperature
Dishwash hot water (typically 60-65°C); for sanitising rinses requiring 82°C+, verify boiler heating capacity.
E. Cooking equipment performance (5 items)
17. Temperature accuracy
Each cooking unit (oven, fryer, plate) thermostat verified with IR thermometer. Within ±5°C.
18. Flame quality
Gas equipment flame should be blue-white, not yellow-tipped or wavy. Yellow flame → air mix wrong → carbon buildup + efficiency loss.
19. Warm-up time
Manufacturer's stated warm-up time tested. Pizza oven typically reaches 450°C in 30-40 min, plate 250°C in 15-20 min.
20. Fan and motor noise
Hood fan, convection oven fan, fridge compressor — no abnormal sound, vibration or smell.
21. Cooling performance
With doors closed, check interior temperature after 2 hours. Fridge < 4°C, freezer < -18°C.
F. Documentation (3 items)
22. CE certificate and Declaration of Conformity
CE Declaration of Conformity delivered for each unit. Asked at annual inspections.
23. Warranty card and service network
Manufacturer warranty (typically 2 years), authorised service list, emergency service phone in writing.
24. User manual (local language)
Local-language manual (Ministry of Industry mandate), maintenance guide, parts catalog. Missing → warranty loss ground.
Don't sign until all 24 items are marked done. For any missing item, note on the protocol with a committed completion date and responsible party.
Practical protocol format
The acceptance protocol should include:
- Date and time
- Item-by-item checklist
- For missing items, completion date and owner
- Operator and installer signatures
- Kitchen photos (each unit + panel + full line)
- Test reports (gas leak, electrical ground, pressure)
Conclusion
Handover takes 2-3 hours. Our recommendation: with the installer's technicians present, have your own chef and electrical/plumbing lead present too. Walk through all 24 items.
This discipline runs the next years' warranty, service and insurance smoothly. On Caccia Pro installations this checklist is standard procedure — ask and we'll share the protocol format.